The dynamic timeline depicts estimated time-use with respect to individual tasks. The NTS project proposal deadline is April 30th, 2013. The NTS Final Report must be completed by December 13, 2013. Click the link below to view the final itteration of the NTS project Schedule.
To conclude on the project I have included a Table 7 which presented a distribution of the hours spent on this project. The Table breaks the project down to hours spent on Tasks. The Tasks in this table correlate to the final NTS project schedule that is included in Appendix 15. Table 7 below presents the distribution of hours spent on the NTS project.
Table 7: Distribution of Hours by Task
The NTS project was completed in 81 percent of the hours that where estimated for the project during the proposal phase. The NTS project totaled 265 engineer hours at a rate of $45.00 per hour totaling $11,925.00. An addition $100.00 was spent on printing and an addition $100.00 was spent on laboratory materials. The total cost of services for this project is $12,125.00.
Finally I would like to thank you for your interest in my project. Please direct any questions or concerns related to the references, laboratory experiments, scale up calculations, and system configuration recommendations to either my email or phone number supplied below.
A public presenation of the NTS project took place on December 6th 2013. A Link to the Final Presenation for the NTS Project is included below.
All 99 samples from the Flow Through Experiment. The three shown below.
Below is an image of the lab rig used for the Flow Through Experiment. The orange bucket at the top is a constant head source. Flow test data can be found in Appendix 12.